FORMER PORTLAND GAS WORKS SITE
MGP Site
Portland, ME
October 2015 – December 2015
$1.9 M
Zero OSHA Recordables
NorthStar performed this remediation project at a former Manufactured Gas Plant (MGP) site (ISS) project located in Portland, Maine. The scope of services consisted primarily of removing over 2,000 cubic yards (cy) of impacted sediment from the Fore River. The work area extended roughly 50 feet from the shore and was required to be performed in the wet, while working from the landside. This necessitated the installation of a heavy section modulus steel sheetpile wall with grouted joints at the shoreline and the use of a long-reach excavator to remove impacted sediment furthest from the shoreline while working from the land side of the sheetpile wall.