EAA A-1 FLOW EQUALIZATION BASIN (FEB)

globe-2Palm Beach, FL

clock-of-circular-shape-at-two-o-clock_318-48022Design: July 2013 – July 2013 Construction: July 2013 -Ongoing

tag$60 M

trophy_iconZero OSHA Recordables

icon-person-128South Florida Water Management District (SFWMD)

 

NorthStar provided design engineering services for the Everglades Agricultural Area (EAA) A-1 Flow Equalization Basin (FEB) from conceptual through Corrected Final / Ready to Advertise design, and engineering during construction (EDC) services. The 15,000 acre EAA A-1 FEB will temporarily detain up to 60,000 ac ft of peak stormwater runoff flows for later controlled release. The concept and implementation of a flow equalization basin is a “first of its kind” project for SFWMD.